Three strategic interchanges on A1, A2 and A3
The works cover the construction of three new road interchanges, each located on a key motorway:
- A1 Bucharest – Pitești: interchange at km 73+100, at the junction with DJ702F, in the Ionești area
- A2 Bucharest – Constanța: interchange at km 90+100, near Dragoș Vodă (Călărași), connecting DJ306 and DN3A
- A3 Bucharest – Ploiești: interchange at km 36+700, in the Gruiu–Nuci area (Ilfov), at the junction with DJ101C
These nodes are designed to improve access between highways and the surrounding local road network, facilitating traffic flows and regional connectivity.
Contractors and investment value
The construction contracts have been awarded as follows:
- Bog’Art will execute the works on A1 and A3
- Bog’Art in association with Oyl Company Holding will deliver the A2 interchange
The total investment value is significant:
- A1 interchange: approx. 41.3 million lei (excluding VAT)
- A2 interchange: approx. 60.5 million lei (excluding VAT)
- A3 interchange: approx. 57.2 million lei (excluding VAT)
Execution timeline and financing
Each interchange is expected to be completed within approximately 10 months, according to project estimates.
The projects are financed through European funds under the Transport Programme 2021–2027, complemented by co-financing from the state budget.
Part of a broader national connectivity strategy
“These interchanges are part of a programme of 36 new nodes on Romania’s motorway network, aimed at improving connectivity between high-speed roads and developing areas, while increasing the sustainability of the infrastructure and supporting economic growth,” explained Ionel Scrioșteanu, State Secretary at the Ministry of Transport.
The initiative reflects Romania’s ongoing efforts to enhance infrastructure efficiency and unlock new development corridors across the country.